Concrete renovation of pylon foundations for the Goor-Hengelo high-voltage power line

Concrete renovation of pylon foundations for the Goor-Hengelo high-voltage power line

Commissioned by TenneT, Balm carried out concrete renovation work on the pylon foundations of the 380 kV high-voltage power line between Goor and Hengelo. In total, this involved the foundations (piles) of 35 high-voltage pylons.

The work involved excavating four concrete foundations around each mast to a depth of approximately 50 cm, sanding and cleaning the concrete, and repairing and levelling it where necessary. A primer coat was then applied, followed by a two-coat coating system. The steel bases on the foundations were sanded and treated with a two- to three-coat component paint. Finally, the ground around the footings was backfilled.

Specialties

Related markets

Work on the Hofgarage and Werfgarage in Amsterdam
View the next project

Work on the Hofgarage and Werfgarage in Amsterdam

The Hofgarage and the Werfgarage, two car parks on the outskirts of the Kattenburg district in Amsterdam, date from 1975. Given their age and the need for modernisation, Balm carried out an extensive refurbishment of both buildings, addressing the structural, architectural and technical aspects of both the interior and exterior.

Curious how we can further assist you with your project?

© Copyright SealteQ 2026 Gebouwd door Saam' Marketing uit Groningen